El Camino High School
Project Information
- Project Location:
- CA
- Approx Contract:
- $900,000
- Status:
- Completed - Jan 2013
- Structure Type:
- Education (K-12)
Scope Of Work
Construction scope of work to be completed in 156 days included:
Modification to existing duct system
Installation of 2 new HVAC units
Abatement and removal of existing exterior building surface
Application of exterior EIFS insulation system
Phased construction and swing shifts to limit impact to school activities.