Featured Project Return to Projects List
Chipotle
Project Information
- Project Location:
- Glassboro, NJ
- Approx Contract:
- $90,000
- Status:
- Completed - Nov 2021
- Structure Type:
- Restaurant
References
- General Contractor:
- A&E Construction
Scope Of Work
- Excavation, back fill & compaction using existing spoils and back fill material.
- Furnish and install schedule #40 PVC above and below slab, sanitary waste & vent piping.
- Furnish and install schedule #40 PVC above and below slab, storm water piping and fittings.
- Furnish and install copper domestic water main piping originating in building.
- Furnish and install copper mains and branch lines for domestic water piping.
- Furnish and install thermal pipe insulation.
- Furnish and install schedule #40 black steel natural gas piping.
- Furnish and install listed fixtures, equipment, materials and accessories.
- Sanitary sewer, domestic and storm water piping shall terminate 5 LF from foundation wall.
- All connections of piping past 5 LF shall be the responsibility of others.
- Flush system and sterilize domestic water piping.