Waste-to-Energy Air Pollution Control Installation
Project Information
- Project Location:
- FL
- Status:
- Completed
- Structure Type:
- Non-Residential Building
References
- Owner:
- Crowder Construction Co.
Scope Of Work
Crowder installed the air pollution control equipment for anew turbine installation at this waste-to-energy electric generating facility. The scope of work included the erection of a 10-module fabric filter system, a spray dryer absorber, ID fan, lime injection system, carbon injection system, structural steel, all associated piping, all associated electrical power, and I/C work. Also included was the erection of the ductwork from the boiler economizer to the APC equipment and from the APC equipment to the stack.