Rye Playland Master Plan Implementation, Rehabilitation, and Upgrades

Project Information

Project Location:
Rye, NY
Approx Contract:
$30,000,000
Status:
Completed
Structure Type:
Government

References

Client:
Westchester County Department of Public Works

Scope Of Work

Overview

LiRo is providing architectural and engineering design, construction administration, and program management services for the Rye Playland Rehabilitation and Upgrades project.

About the Project

At the core of the project deliverables is a comprehensive scan of the entire Playland park, compiled from both aerial drone imagery and scans from our cutting-edge laser machines on the ground. Playland Park was originally constructed in the 1920s and is listed on the National Register of Historic Places.

Projects included in the Phase I Capital Construction Program are:

Rehabilitation of the historic Carousel and Derby Racer rides, including roofing replacement, upgrades to fire protection and roofing systems, painting, and structural stabilizations (foundations)

Upgrades to the seven south bathhouse storefront shops in preparation for tenant build-out, including upgrading fire protection, lighting, electrical, and mechanical systems

Rehabilitation of the arcades including compliance with all building and handicapped access codes, structural stabilization, and roofing and siding replacement

Rehabilitation of the Playland employee areas and restroom areas, including building compliance, roofing and siding replacement, and upgrades to plumbing, fire protection, and mechanical systems

Replacement of existing incoming switchgear including the construction of a new switchgear building and installation of new primary electrical service

Projects to be included in the Phase II Capital Construction Program are:

Structural rehabilitation of the historic tower foundations including subsurface investigations, shoring of the existing tower, and rehab of the existing timber foundation piles

Reconstruction of the Playland food areas, including compliance with all building and handicapped access codes, structural stabilization, and upgrades to lighting, electrical, and mechanical systems

Restoration of the administration building’s interior including modification to the layout and structural stabilization

Rehabilitation of the Fountain Plaza entrance area including the removal of existing mini golf course, removing existing asphalt paving, installing new plaza pavers, and upgrading and/or replacing plaza utilities

Rehabilitation and redesign of the main parking lot, including restriping, milling and paving, and installation of new ticket booths, islands, landscaping, bio-swales, and drainage systems

Outcome

This project is currently in design development.

Project Images

#
#
#
#
Share URL copied!
https://www.thebluebook.com/iProView/882767/the-liro-group/subcontractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.