Benton Harbor Water Filtration Plant
Project Information
- Project Location:
- Benton Harbor, MI
- Approx Contract:
- $2,000,000
- Status:
- Completed - Jan 2013
- Structure Type:
- Sewage / Water Treatment Plant
References
- Owner:
- City of Benton Harbor
- Architect:
- Abonmarche
- General Contractor:
- Davis Construction
- Client:
-
Rob
Kaliniak
-
Project Manager
(616) 456-0059Davis Construction
Scope Of Work
Addition and renovation to existing plant. Entire new electric and SCADA system, including MV Switchgear and Motor Control Centers, and 1,000KW whole plant generator.