![Logo](https://pvu.thebluebook.com/inc/img/qp/1699052/deschutes-construction-corp-logo.png?quality=90&width=120&height=120&mode=pad)
Deschutes Construction Corp.
Redmond, OR 97756
Featured Project Return to Projects List
US 97 Sunriver Bridges
Project Information
- Project Location:
- OR
- Status:
- Completed
- Structure Type:
- Bridge
Scope Of Work
Deschutes Concrete Construction was hired as a sub-contractor by Knife River to construct 5 bridges along US97 near Sunriver, OR. This project took place from the fall of 2009 to the spring of 2011. 2500 CY of concrete was cast in place to form the footings, bents, decks and impact panels. An Allen bridge deck finisher was used to place and finish the concrete decks. All the superstructures were pre-stressed concrete slabs and box beams.