The Fairmont Water Treatment Plant
Project Information
- Project Location:
- Fairmont, MN
- Approx Contract:
- $30,000,000
- Status:
- Completed
- Structure Type:
- Sewage / Water Treatment Plant
Scope Of Work
The Fairmont Water Treatment Plant is a new 41,000 square foot water treatment plant located near Budd Lake in Fairmont, MN. The plant can handle up to 5.4 million gallons per day using conventional lime/soda ash softening, sand filtration, and granular activated carbon absorbers. The plant also generates sodium hypochlorite for chlorine disinfection.
Additional project highlights:
400,000-gallon clear well
Two 210,000-gallon backwash reclamation basins
Eight filter cells
8,900 cubic yards of concrete poured
Process pipe/valves ranging from 4” to 36”
On-site museum