Scope Of Work
SCOPE
TRANE 10 TON 14 SEER PACKAGED HEAT PUMP SYSTEM 208-230V/3-PHASE; STANDARD EFFICIENCY
MODEL#WSC120H 3R0B005D
THERMOSTAT: WI-FI ECOBEE
* Install (2) 10-ton Package Unit
* Install Spiral Ducting in Gym with Registers for both units
* Cut in New Return with Return Grills
* Electrical Whip with 3 Phase Fused Disconnect Box
* Run thermostat wire and Install New Thermostats
* (MPU) Main Panel Upgrade with New Breakers for Both Systems.
* Run Electrical Wiring to Rooftop and through the back of stairs to other side where 2nd unit will be installed.
* Seal all penetrations made for ductwork water tight, the existing openings (window) are made out of ply wood. We will be installing something more weatherproof.. possibly sheet metal transition.
* Crane rental
Challenges? Working around the existing layout
Solutions? We troubleshooted adjusted the layout so that it was aesthetically pleasing (ducting)
Customer loved the finished work, and rehired us for some HVAC chang-outs for their offices.