Featured Project Return to Projects List
AEP Michiana Service Center
Project Information
- Project Location:
- Niles, MI
- Approx Contract:
- $30,000,000
- Status:
- Completed
- Structure Type:
- Office Building
Scope Of Work
It took 36 flat bed trucks filled with steel for the exterior envelope of the facility
There were a couple of interesting phases to this project. We received the steel for the main building in December and were setting steel all through the winter months in Western Michigan. The second interesting phase was that eight months into the project, the State of Michigan went into a Stay-at-Home order. Fortunately, this project was deemed as “critical” because it was for a utility company. We were able to work through the government order and maintain a schedule that would achieve Certificate of Occupancy by the end of the year.
Additional Facts:
106,825 square feet of heated floors
8 electric vehicle charging stations
38 overhead doors to access the main service center
9.7 acres of equipment lay-down area