Featured Project Return to Projects List
Abington Regional Wastewater Treatment Plant
Project Information
- Project Location:
- Chinchilla, PA
- Status:
- Completed
- Structure Type:
- Sewage / Water Treatment Plant
References
- Owner:
- Abington Regional Wastewater Authority
- Architect:
- Gannett Fleming Engineers
Scope Of Work
This assignment for Abington Regional Wastewater Authority includes construction of a brand new bio-solids management building, a new process operations building and a new headworks building. Quandel is also:
Converting the existing filter press building into a new chemical feed building
Renovating the main pump station and the control building
Constructing two new concrete sludge holding tanks and two new concrete aerobic digesters
Converting six aeration tanks into three new bioreactors
Renovating final clarifiers #1 and #2
Converting the existing aerobic digester into new final clarifier #3
Adding a second UV disinfection system and re-aeration tank
Demolishing the abandoned chlorine contact tank
New treatment equipment includes grit removal, centrifuge, chemical feed systems, clarifier mechanisms, sludge grinders, blowers, dry pit submersible pumps, bar screens, compressed gas mixing system, coarse and fine bubble diffuser systems, new process monitoring and control system.