12 Ave School Water Distribution & Sewer lines

Project Information

Project Location:
Miami, FL
Status:
Completed - May 2016
Structure Type:
Misc Project
Services Rendered:
Underground Utilities--Contractors:
Civil Engineering Permitting
Water and Sewer Construction
Civil Engineering Design
Water Design and Permitting
Water Main Extension
Water Distribution Systems
Sewage Collection Systems
Site Development Utilities

References

Architect:
Engineer Rudy Ibarra PE
General Contractor:
Florida Pipeline Company

Scope Of Work

Design,  Construction and Conveyance of a new 12” Watermain extension to service a new school.  The work consisted of the installation of approximately 270’ of new 12” ductile iron pipe, including new water service connections and upgrading the sewer line lateral. The maintenance of traffic plan consisted of a modified roadway closure to facilitate installation. Restored the roadway. The waterline was tested, certified and conveyed to Miami Dade Water & Sewer Department. System was constructed on time and within budget.

Design & Permitting tasks shown below

  1. Allocation letter DERM                                                           
  2. Survey including roadway                                                                                                                 
  3. Dry run Miami Dade Public Works (water & sewer)             
  4. Dry run Miami Dade Public Works (roadway section)          
  5. Final submittal Water & Sewer                                              
  6. DERM plans review                                                                                                           
  7. Miami Dade Fire Department                                                                                                                
  8. Florida Department of health                                                 
  9. DERM Water permit                                                              
  10. DERM Sewer permit                                                              
  11. Public works section                                                                                                       
  12. National pollution discharge NPDES                                     
  13. Submit & Approval of  MOT Plans                                         
  14. Public works contractors permit                                 
  15. Pre-construction meeting with City                                       

Construction Tasks for the project are itemized below:

  1. Mobilization                                                                            
  2. NPDES setup                                                                                                                                   
  3. Street Crossing Water line                                                    
  4. Onsite waterline install                                                           
  5. Onsite sewer install                                                               
  6. Onsite plumbing rough                                                          
  7. Backfill and density testing                                                    
  8.  Inspection rough                                                         
  9. Testing tapping sleeve                                                             
  10. Testing tapping valve                                                               
  11. Road plates & MOT ( concurrent with tasks 1-4)                  
  12. Milling & Resurfacing                                                          
  13. Temp pavement markings                                                     
  14. Final pavement markings                                                      
  15. Restoration of sidewalk                                                                     
  16. Line & grade inspection                                                                                             
  17. Pre- final inspection                                                               
  18. Water pressure test                                                               
  19. Water backflow certification                                                  
  20. Water bacteriological test                                                      
  21. Engineer’s certification                                                          
  22. HRS Clearance letter                                                             
  23. Contractors bill of material                                                     
  24. Water & Sewer pre final & punch list                                    
  25. Water & Sewer final                                                               
  26. Final public works                                                                                                                                                                           

Project Images

#
#
#
#
#
#
#
#
#
#
#
Share URL copied!
https://www.thebluebook.com/iProView/1663967/florida-pipeline-company/subcontractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.