Design, Construction and Conveyance of a new sewer collection system and removal of an existing pump station and force main for an existing commercial building. The pump station was a dual submersible 5 hp. private station that connected to the local utility system. The new sewer line consisted of 400’- 8” PVC gravity sewer line. Developed and maintained MOT. Full pavement restoration. System was constructed on time and within budget.
Design & Permitting tasks shown below
Allocation letter DERM
Survey including roadway
Dry run Miami Dade Public Works (water & sewer)
Dry run Miami Dade Public Works (roadway section)
Final submittal Water & Sewer
DERM plans review
Miami Dade Fire Department
Florida Department of health
DERM Sewer permit
Public works section
National pollution discharge NPDES
Submit & Approval of MOT Plans
Public works contractors permit
Pre-construction meeting with City
Construction Tasks for the project are itemized below:
Mobilization
NPDES setup
Onsite sewer install
Onsite plumbing rough
Backfill and density testing
Inspection rough
Road plates & MOT
Milling & Resurfacing
Temp pavement markings
Final pavement markings
Restoration of sidewalk
Line & grade inspection
Pre- final inspection
Engineer’s certification
HRS Clearance letter
Contractors bill of material
Water & Sewer pre final & punch list
Water & Sewer final
Final public works