Project Information
- Project Location:
- Camp Pendleton, CA
- Approx Contract:
- $500,000
- Status:
- Completed
- Structure Type:
- Military
References
- Architect:
- GMH Associates, Inc
Scope Of Work
Design - Build
Vertical Construction
Contract Value: $597,776
DOR: GMH Associates, Inc.
This Field Hygiene Facility is basically an open air facility used for
washing/shaving/ hand washing purposes. The facility is designed
to accommodate 440 marines per day for washing/shaving and 1,320 per day for hand washing. The building is an open structure with a masonry wall constructed in the middle of the building spanning the length of the structure. Attached to both sides of the masonry wall are multi-station stainless steel sinks with a shelf and mirror attached.