Featured Project Return to Projects List
CLT Jet Fuel And Avgas Facility Expansion / Renovation
Project Information
- Project Location:
- Charlotte, NC
- Status:
- Completed
- Structure Type:
- Storage Facility / Warehouse
Scope Of Work
The firm designed the expansion and renovation of the joint use Wilson Air / Bank of America fuel storage and dispensing facility at Charlotte/Douglas International Airport. Five new 20,000 gallon steel and two new 12,000 gallon steel Jet-A tanks were installed. One new 20,000 steel Avgas tank was also designed and installed.
PROJECT HIGHLIGHTS:
Refurbish Tanks
New Jet Tanks
New Avgas Tank
Two Fuel Cabinets
Load / Unloading Stations
The work scope included refurbishment of two existing 12,000 gallon steel tanks, two new remote fueling cabinets were also designed to allow fueling aircraft directly on the parking apron. An Avgas and Jet load / unloading station was also constructed.