San Diego River Bridge Double Track

Project Information

Project Location:
San Diego, CA
Status:
Completed
Structure Type:
Road / Highway

Scope Of Work

THE PROJECT

Construction of the new San Diego River Bridge Double Track (SDRBDT) within the MTS/San Diego and Arizona Eastern (SD&AE) right-of-way included construction of one mile of track and embankment supported on soft clays.  Much of this new track was to be constructed near existing structures.   

THE CHALLENGE

Adjacent structures were susceptible to excessive settlement due to embankment-induced clay consolidation. The main challenge was working between the live train traffic and existing structures. The tight construction schedule required creative ground improvement solutions to accelerate construction. Coordination of HBI’s work with the railroad’s Employee In Charge (EIC) was required. Treatment depth in excess of 65 feet was also necessary to meet the settlement requirement.   

THE SOLUTION

A rigid inclusion ground improvement solution proposed, designed, and constructed by HBI provided reinforcement in the upper layers of soil, which compaction grouting would not have provided. Rigid inclusions were installed between live railroad traffic and existing buildings. The area treated is 26 feet wide by 1,500 feet long.  

"Hayward Baker played an integral role in the design phase modifying the ground improvement methods that balanced the budget with the schedule, ultimately providing the owner with a better product." -Matthew Heminover, project manager for MCTCJV

Share URL copied!
https://www.thebluebook.com/iProView/1717506/keller/subcontractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.