Company Info

  • Size 500+ Employees
  • Annual Vol Undisclosed

Featured Project Return to Projects List

Suncor Pond 5

Project Information

Project Location:
Calgary, Alberta, Canada, CA
Status:
Completed
Structure Type:
Utilities

References

General Contractor:
Hayward Baker, Inc.
Client:
Suncor Energy

Scope Of Work

THE PROJECT

Suncor’s Pond 5 is approximately 1.6 km by 2.5 km in plan dimensions and 40 m deep. The pond is filled with fluid-like clay tailings with shear strengths typically less than 1 kPa and average water content of 114%. Mine regulators in Alberta required construction of a permanent cap on the pond and reclamation of the land. A solution was needed to dewater the fine tailings and increase their shear strength to allow for construction of the cap.

THE CHALLENGE

Northern Alberta is a remote location with harsh winter working conditions. The work platform consisted of a floating cover over fluid low-strength tailings, presenting equipment and personnel safety issues. HBI was tasked with finding a way to anchor the wick drains at a depth of 16 m in soft fluid low strength tailings.

THE SOLUTION

HBI safely and efficiently installed 6.2 million linear meters of wick drains from on top of the floating cover over the soft tailings. The wick drains produced between 0.5 to 1.5 million gallons of water per day, rapidly accelerating the shear strength increase in the tailings, which allowed for subsequent permanent capping of the pond. HBI utilized a proprietary data acquisition system to facilitate layout of the wicks, provide installation information, and produce as-built drawings. 

HBI was awarded Suncor’s “President’s Operational Excellence Award for Personnel Safety.”

Project Images

#
#
Share URL copied!
https://www.thebluebook.com/iProView/1717506/keller/subcontractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.