GT ADVANCED TECHNOLOGIES Merrimack Facility Expansion
Project Information
- Project Location:
- Billerica, MA
- Approx Contract:
- $40,000,000
- Status:
- Completed
- Structure Type:
- Office Building
References
- Architect:
- Industrial Facilities Design, Inc.
Scope Of Work
JMC constructed a new addition to accommodate GT Advanced Technologies' expanded production capacity as its world headquarters in Merrimack, NH. This high-tech company develops and manufactures crystal growth technology and advanced materials for the electronics, solar, and LED industries. The project involved significant HVAC and process systems work to support the company's enhanced operations.
Project Features
37,500 sf total
9,500 sf addition
Renovations to existing building
12 new furnaces
Four 1-MW Caterpillar standby generators
Two cooling towers
Two rooft op units
Installation of pumps, VAVs, and 12" PVC piping
Accommodated second project added midway