Gulf Energy Clean Energy LNG Tanks
Project Information
- Project Location:
- Pascagoula, MS
- Status:
- Completed - Dec 2010
- Structure Type:
- Power Generation & Distribution
References
- Owner:
- Gulf Clean Energy Project
- Architect:
- n/a
- General Contractor:
- n/a
Scope Of Work
The Gulf LNG Clean Energy facility welcomes a ship every three days for LNG unloading with a send out capacity of 1.3 billion cubic feet per day (bcf/d). In 2008, Baker contracted to build two 160,000 cubic-meter storage tanks with a 6.6 bcf combined capacity. Baker's scope for two containment tanks included the pile caps, concrete walls, and concrete roof.