Featured Project Return to Projects List
MARINE PARKWAY
Project Information
- Project Location:
- NY
- Status:
- In-Progress
- Structure Type:
- Parking Garage
References
- Owner:
- TBTA
Scope Of Work
This project is a combination of five contracts under one bid that covers Electrical & Mechanical Rehabilitation of Lift Bridge, Miscellaneous Structural Steel Repairs, Lead Abatement (Class 1A / SP10) and Painting of Structural Steel and Fire Standpipe System.
Scope of Work:
Complete replacement of moveable bridge electrical system
Mechanical upgrades for the machinery system
Lead Abatement and Painting
Installation of new fire stand pipe system
Architectural upgrades and repairs
Various structural steel repairs,
Furnish and install structural monitoring system
Asbestos Abatement
Duration: 36 Months
Worktype: Moveable Bridge Rehabilitation
Contract Award Date: December 2015
Contract Completion Date: In Progress
Contract Value: 98,500,000.00 USD