Groundwater Barrier System Installation

Project Information

Project Location:
Rodeo, CA
Approx Contract:
$1,000,000
Status:
Completed
Structure Type:
Misc Project

Scope Of Work

Project Details

Trihydro engaged ICS to install a groundwater barrier system at the marine terminal area within the Phillips 66 San Francisco Refinery in Rodeo, California. The system extracts groundwater from forty three (43) onsite extraction wells. The scope of work included grading, asphalt paving, the installation of dual contained conveyance piping and air line piping, installation of pipe supports and concrete pads

Field Tasks

Grading and installation of new asphalt with containment curb
Set well vault and install concrete skirts
Air knifing holes for 218 pipe supports and 75 bollards
Installed 218 free standing pipe supports and 75 bollards
Installed 38 concrete pads for extraction pump boxes
Installed over 2,200 linear feet of dual contained (3-inch inside 6-inch) CPVC pipe including expansion loops and valves

Field Tasks

Installed over 700 linear feet of Schedule 80 carbon steel pipe
Make tie-ins to sumps
Hydro- static test all water carrier pipe and pressure test all air line piping
Removed two (2) existing sump pumps and install two (2) new Gould Pumps

Project Images

#
#
#
#
Share URL copied!
https://www.thebluebook.com/iProView/366419/innovative-construction-solutions/subcontractors/
Facebook
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.