Petro Fuels Floating Dock and Pipe Rack
Project Information
- Project Location:
- LA
- Status:
- Completed - Jan 2020
- Structure Type:
- Misc Project
References
- Client:
- Petro Fuels
Scope Of Work
Boh Bros. found itself battling high river levels unseen obstructions during a floating barge dock associated pipe rack Mt. Airy, Louisiana. end, terminal operator, PetroFuels, significantly boosted their dock capacity to accommodate four 54- by 300-foot barges at one time. The terminal, situated just south of the Gramercy Bridge, ships oil, liquid asphalt light oil to destinations along Gulf Mexico Eastern Seaboard. Boh constructed pipe racks around existing terminal tanks set a 20-foot wide structural steel pipe bridge across Hwy 44 to new floating barge dock. Boh also drove mooring berthing piles, set a 100-foot long articulating truss for new dock.