Laramie WTP Clearwell & Piping
Project Information
- Project Location:
- CO
- Approx Contract:
- $4,000,000
- Status:
- Completed - Oct 2016
- Structure Type:
- Sewage / Water Treatment Plant
References
- Owner:
- City of Laramie
Scope Of Work
Engineer: HDR Engineers, Inc.
Description: New construction consisting of the following: Wet well, pump station, control valve vault, valve manholes, 30” & 42” buried Ductile Iron Pipe, along with associated sitework. Project Details: 1. Superintendent: Jason Wesseling 2. Project manager: John Jacob 3. Start date: 9/28/2017 4. Number of contract days: 425 5. Extension of contract from change orders: 34 days 6. Actual days to completion: 412 7. Substantial completion: 10/19/2016 8. Final completion date: 11/24/2016 9. Original contract value: $3,216,824.00 10. Value of Change orders: $64,644.00 11. Number of change orders: 14 12. Final contract value: $3,281,468.00 13. Percentage of self-performed work: 79%