Apple – Newark Data Facility
Project Information
- Project Location:
- Newark, CA
- Status:
- Completed
- Structure Type:
- Data Centers - Mission Critical
Scope Of Work
36,000 Sq. ft. server facility Phase 1 and Phase 2
• 4600 tons cooling
• 5 Cooling Towers with water storage totaling 320,000 gal.
• 1 Chilled Water storage tank for 100,000 gal.
• Electrical equipment to provide 1.6 MW, N+1 redundancy
• Providing process piping, HVAC, mechanical piping and plumbing.