Tropical Farms WWTP Neutralizer Facility
Project Information
- Project Location:
- Stuart, FL
- Approx Contract:
- $49,800
- Status:
- In-Progress - Jun 2015
- Structure Type:
- Sewage / Water Treatment Plant
References
- Owner:
- BGA, Inc.
- Architect:
- Holtz Consulting Engineers, Inc.
- General Contractor:
- BCR Environmental
- Client:
-
Todd
Chambers
-
Production Coordinator
(904) 819-9170BCR Environmental
Scope Of Work
Campbell Plumbing was selected by BCR Environmental, Inc. to install not only domestic water, sanitary sewer and floor drains, but also BCR's proprietary, energy saving, and by-product producing Neutralizer system. Campbell was able to install this technically complex system of piping, connections, holding tanks and chemical handling components using solely in-house manpower and resources. In fact, it was because of this ability to install both the conventional plumbing and the Neutralizer system that led to Campbell's selection to the project team. This project has been such a success that Campbell was selected to perform the same scope of work on the neighboring city of North Jensen Beach's new WWTP Neutralizer Facility.