Campus Electric Capacity Phase 2
Project Information
- Project Location:
- Columbus, OH
- Status:
- Completed
- Structure Type:
- Mixed Use
Scope Of Work
Ohio State needed to increase its electric capacity by this project – Campus Electric Capacity Phase 2 (New Substation). The general contractor engaged our services to shore up and protect the existing AEP control building that had to remain in service. Righter designed and built a soldier pile/lagging wall with tiebacks for the 18 foot deep excavation to protect the existing building and ensure that it stayed in service.