Scope Of Work

Graycor Industrial performed civil/mechanical and structural construction for the Coker Material Terminal located at BP’s facility in Whiting, Indiana. Project consisted of two phases: Foundations and underground utilities, and structural, conveyors and piping.

Graycor self-performed the concrete, structural steel, piping, millwright, equipment setting and commissioning work.

Foundations and Underground Utilities:

182 auger cast-in-place piles:

5,200yd3 of poured foundations/pile caps/access ramps

3,350 feet of underground piping    

7,600yd2 of Asphalt paving

4,400 linear feet of rail

New MCC room, duct banks and grounding

Structural, Conveyors and Piping:

400 tons of structural steel (towers)       

2,331 feet of 54” conveyors (10 total)

11,500 feet of service piping      

Pump skids / equipment setting              

Heat tracing and insulation

Commissioning assistance

Project Images

#
#
#
Share URL copied!
https://www.thebluebook.com/iProView/974530/graycor-inc/general-contractors/
Facebook
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.